24x24 Garage Concrete Slab Yardage & Turnkey Cost Calculator

Calculate exact cubic yards, 80-lb bags, rebar grid, wire mesh, and turnkey contractor installation cost for a standard 24x24 ft double car garage slab.

Regional Market Calibration:Adjusts trade labor, concrete mix, and building codes to local city averages.
Popular Dimension Presets:
Engineered Slab Cutaway Cross-Section (ACI 302)Slab Thickness: 4" Commercial Grade
Broom Finished Concrete Surface4,000 PSI Poured Concrete (4" Slab)#4 Rebar (18" o.c.)10-Mil Heavy Duty Vapor Barrier Membrane (ASTM E1745)4" to 6" Compacted #57 Crushed Stone Base (95% Modified Proctor)

Cross-section demonstrates structural reinforcement elevation on concrete chairs per ACI 302.

Project Dimensions & Material Inputs

Total Ready-Mix Concrete Required

9.78 Cubic Yards (Order 10.0 ydΒ³)

Pre-Mix 80-lb Bag Equivalent

441 Bags (4000 PSI Air-Entrained)

Contractor Bill of Materials (BOM) Breakdown

Item / Material SpecQuantityUnit / PackageInstallation Notes
4000 PSI Ready-Mix Air-Entrained Concrete10.0Cubic YardsIncludes 10% subgrade variance & spillage
#4 (1/2") Deformed Steel Rebar (18" o.c. grid)5920-Ft Sticks1167 lin ft (780 lbs) with 15" lap splices
#57 Crushed Stone Base (4" compacted depth)14.8Tons15% mechanical compaction allowance included
10-Mil Heavy Duty Polyethylene Vapor Barrier828Square FeetASTM E1745 Class A puncture resistance
3-Inch Concrete Rebar Support Chairs72ChairsEnsures rebar is suspended in upper third of slab
Pre-molded Asphalt Expansion Joint Strip108Linear FeetIsolates slab from adjacent foundation walls

Estimated Project Cost Range (DIY vs. Turnkey Contractor)

National Average
DIY Raw Materials Only
$3,605 – $4,364

Cost of raw lumber, concrete, shingles, wire, or stone without equipment rentals or labor.

Licensed Contractor Turnkey
$6,120 – $9,216

Full installation: permits, site prep, skilled trade labor, equipment, and structural warranty.

Estimated Sweat Equity
~$3,684

Average trade labor savings if executed as a skilled DIY homeowner project.

Verified Trade Contractor NetworkScope Auto-Synced

Compare Up to 3 Free Quotes from Licensed Local Contractors

Skip the heavy equipment rentals, structural liabilities, and municipal permit delays. Connect directly with pre-screened, licensed, and insured trade specialists in National Average.

100% Free Service Zero Obligation Pre-Calculated Project Specs
⚑ Local pros respond in < 2 hours

24Γ—24 Slab Geometry & Bag Conversion Formula

Rendering formula...

Engineering Math for 30' Γ— 24' (4" Slab at 4000 PSI)

  1. Slab Area = 30 ft Γ— 24 ft = 720 sq ft.
  2. Center Slab Volume = 720 sq ft Γ— (4 Γ· 12 ft) = 240.0 cu ft (8.89 ydΒ³).
  3. Control Joint Cut Quadrants: Four 15' Γ— 12' panels cut to depth of 1".
  4. Total Net Concrete = 8.89 ydΒ³. Factoring 10% subgrade waste = 9.78 ydΒ³ (Dispatch order: 10.0 yards).
  5. Rebar Calculation: 17 runs Γ— 30 ft + 21 runs Γ— 24 ft = 1167 linear feet (#4 rebar = 780 lbs).
  6. Sub-base Gravel (4" depth): 8.89 ydΒ³ Γ— 1.45 tons/ydΒ³ Γ— 1.15 compaction = 14.8 tons.
Engineering Tip: Under National Average conditions, control joints must be saw-cut within 12 hours of pouring to prevent random shrinkage cracking. Concrete test cylinders should achieve 4000 PSI at 28-day cure.

Quick Reference Sizing & Coverage Table

Standard commercial specifications and pre-calculated project benchmarks.

Pre-Calculated
ThicknessVolume (Net)Order With 10% Waste80-lb Bag EquivalentTurnkey Contractor Cost Range
4 Inches7.11 ydΒ³7.82 Cubic Yards352 Bags$4,600 – $6,800
5 Inches8.89 ydΒ³9.78 Cubic Yards440 Bags$5,500 – $8,100
6 Inches10.67 ydΒ³11.74 Cubic Yards528 Bags$6,500 – $9,600
4" Slab + 12" Edge10.43 ydΒ³11.47 Cubic Yards516 Bags$7,200 – $10,500
ACI 302.1R Guide for Concrete Floor Construction

ACI 302.1R Joint Spacing & Compressive Strength

A 24x24 slab must have control joints cut into 4 equal quadrants (12' Γ— 12' panels) at a depth of 1/4 the slab thickness (1" deep for a 4" slab) within 12 hours of pouring. Concrete mix design must be minimum 3,500 to 4,000 PSI with air entrainment.

Frequently Asked Questions

How many yards of concrete do I need for a 24x24 garage slab?

At a standard 4-inch thickness, a 24x24 slab requires 7.11 cubic yards of concrete. With the recommended 10% margin for grade variations and spillage, you should order 8.0 cubic yards from the ready-mix plant.

Should I pour a 4-inch or 6-inch garage slab?

A 4-inch slab is sufficient for passenger cars and light pickup trucks. If you plan to install a 2-post car lift, store heavy RVs/machinery, or use a heavy rolling floor jack, pour 5 to 6 inches with a #4 rebar grid.

How much does a 24x24 concrete slab cost installed in 2026?

Turnkey cost (excavation, 4" crushed gravel base, forms, rebar, 4,000 PSI concrete, pouring, and broom finishing) averages $8.00 to $12.00 per square foot, or $4,600 to $6,900 total.

Can I mix 350 bags of concrete myself in a rental mixer?

It is not recommended. Mixing 350 bags requires lifting 28,000 lbs of dry material and pouring for 8+ hours, which causes cold joints (weak failure seams between batches). Order ready-mix concrete by truck.